Language

News

Dry Cullet Cleaning & Sorting: Process Guide and Upgrade Plan for Existing Wet-Washing Lines

Recycled cullet dry cleaning &

automatic sorting line proposal

Shanghai SAISEC Intelligent Equipment Co., Ltd.

Recycling business — SAISEC

Cullet is the primary raw material for daily-use container glass. It carries large amounts of contaminants: ceramics, stones, soil, paper, plastics, aluminium caps and rings, iron caps and residual organics. Ceramics, stones and metals severely affect glass quality and must never reach the furnace — they must be removed completely.

II. The dry cullet cleaning and automatic sorting process

Hopper feeding with dual feeders — weighing by belt scale — simultaneous magnetic separation by drum magnet and magnetic pulley — circular vibrating screen for grain-size screening — oversize to the crusher — neck separation screen removes bottle necks, which are conveyed away for further processing — cullet within spec goes straight downstream — trommel screen refines grain size — three or four size fractions go to three or four optical sorters — the sorters separate opaque refractories and coloured flakes — after label removal by the label-abrasion machine and density separator, cullet returns to the optical sorters for re-purification.

IV. The value of dry cullet cleaning

1. Dried cullet product with low moisture. A plant using 100,000 t of cullet per year saves 4 percentage points of moisture going into the furnace — 4,000 tonnes of water. Evaporating it would burn 85 m³ of natural gas per tonne — 340,000 m³ per year, nearly one million RMB — money no longer wasted;

2. CSP (stones and ceramics) and aluminium content far below what wet washing and manual sorting can achieve, raising yield and greatly extending furnace life — economic benefits worth millions per year;

3. High automation: one line needs only 1–2 operators. Every 100,000 t of cullet saves 7–10 workers;

4. No wastewater, and a neat, orderly site that raises the customer's image with government and downstream customers;

V. Implementation and upgrade process

1. First, survey the raw material: the proportion and characteristics of contaminants and mixed colour;

2. Set project targets, product contaminant limits and output requirements;

3. Sign a process-upgrade design contract; the supplier drafts the upgrade plan and the equipment list;

4. Sign the equipment procurement contract;

5. If construction design service is required, a separate design contract is signed and the supplier provides construction drawings.

← All news